A Rapid City, S.D., company has landed a $2.6 million contract to rebuild a flood-damaged causeway that connects the city of Pierre to LaFromboise Island on the Missouri River.
The Army Corps of Engineers awarded the contract to Ainsworth-Benning of Wyoming Inc., one of three bidders on the project. The work is expected to start in mid-April and take about six months to complete.
Crews will reconstruct the 1,400-foot-long causeway, including replacing a 500-foot-section washed away by floodwaters last summer. City crews also will work on water lines to four city water wells on the island.
The causeway is a popular place for people to walk, bike and fish.
Copyright 2025 Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.
Was this article valuable?
Here are more articles you may enjoy.
OpenAI And Microsoft Sued Over Murder-Suicide Blamed on ChatGPT
Wells Fargo Sued by Ex-Manager Who Said Bank Faked Diversity
Zillow Deleting Climate Risk Scores Reveals Limits of Flood, Fire Data
Rare Weather Warning Issued as Strong Gusts Fuel Colorado Wildfire Threats