San Francisco fire officials say work being done by a steel subcontractor is believed to have ignited a massive blaze that barreled through an apartment building construction site in San Francisco in March.
The San Francisco Chronicle reported Monday that the president of Petaluma-based TC Steel, Tom Cleary, was cited and fined $1,000 this month for being out of compliance with the city’s fire code.
Officials say the March 11 blaze likely started from sparks that came from cutting and welding work.
Neither Cleary nor TC Steel could be immediately reached for comment.
The fire gutted the 172-unit residential complex building and damaged three other structures in the Mission Bay neighborhood.
A report estimated damage at about $40 million.
Was this article valuable?
Here are more articles you may enjoy.
US Weighs Tougher Auto Import Rules to Accelerate Reshoring
A 16,000% Problem: Why Workers’ Comp Can’t Get Drug Costs Under Control
Travelers to Expand Homeowners Insurance Offering in California
PwC Pays $166 Million to Settle HK Evergrande Audit Probe