The Seattle Transportation Department admits it made a mistake with deicer that caused some accidents Dec. 2 and shut down the West Seattle Bridge.
Road maintenance manager Steve Pratt told a city council committee Tuesday they were trying to get ahead of anticipated freezing weather and Monday night football traffic when they sprayed magnesium chloride on the roadway that afternoon.
KIRO-FM reports it was too warm at the time – more than 40 degrees – and the operator mistakenly applied twice the recommend amount – 30 gallons per lane mile, instead of 15.
The result? Instead of preventing a slick roadway, the deicer created slippery pavement.
The department says the road crew will be trained to prevent making the same mistake again.
Was this article valuable?
Here are more articles you may enjoy.
LA County Told to Pause $4B in Abuse Payouts as DA Probes Fraud Claims
Why 2026 Is The Tipping Point for The Evolving Role of AI in Law and Claims
Cape Cod Faces Highest Snow Risk as New Coastal Storm Forms
FM Using AI to Elevate Claims to Deliver More Than Just Cost Savings