It’s going to cost nearly $2.5 million more than first thought to rebuild Belmar’s boardwalk that was destroyed by Superstorm Sandy.
The New Jersey town’s engineering firm underestimated the original $6.6 million dollar project.
Belmar administrator Colleen Connolly tells the Asbury Park Press Birdsall Engineering based the reconstruction on the walkway being 25 feet wide. However, the boardwalk is wider than that in spots.
Connolly also says beach ramps need to be reconfigured to comply with the Americans With Disabilities Act.
The town council will review the change order at its Wednesday night meeting.
Copyright 2025 Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.
Was this article valuable?
Here are more articles you may enjoy.
Pacific Northwest Braces for Even More Flooding Rain This Week
LA Fires Push Insurers’ 2025 Disaster Losses to $107 Billion
Tesla Drivers Are Buying Escape Tools and Cars to Avoid Getting Trapped Inside
‘Dream Is in Sight:’ Chamber, Reinsurers, Insurers Urge Florida to Stay the Course