It’s going to cost nearly $2.5 million more than first thought to rebuild Belmar’s boardwalk that was destroyed by Superstorm Sandy.
The New Jersey town’s engineering firm underestimated the original $6.6 million dollar project.
Belmar administrator Colleen Connolly tells the Asbury Park Press Birdsall Engineering based the reconstruction on the walkway being 25 feet wide. However, the boardwalk is wider than that in spots.
Connolly also says beach ramps need to be reconfigured to comply with the Americans With Disabilities Act.
The town council will review the change order at its Wednesday night meeting.
Copyright 2025 Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.
Was this article valuable?
Here are more articles you may enjoy.
Wells Fargo Whistleblower on Sham Interviews Wins Right to Sue
North Carolina Motorist Tells 911: Eagle Dropped a Cat Through the Windshield
The 2025 Atlantic Hurricane Season: Rapidly Intensifying Storms Between Long Lulls
State Farm Sued Over Policies Backed by Distressed Insurer PHL